On the Rovno nuclear power plant ahead of schedule and completed the repair

На Ровенской АЭС досрочно завершили ремонт Nuclear power plants connected to the fourth block to the grid.

Rivne nuclear power plant (NPP) on August 21 in 18.55 connected to the grid of the fourth unit after conducting medium planned maintenance. This was reported by the press service of the state enterprise Energoatom on Tuesday, August 22.

According to the report, the repair was completed ahead of schedule – 48 days instead of the planned 52.

Kwork.ru - услуги фрилансеров от 500 руб.

Thus, as of Tuesday morning are in the works 11 from 15 power units of four existing nuclear power plants in the country.

At power unit №3 of Zaporizhzhya NPP – 188 day average planned repairs at unit No. 1 of Yuzhno-Ukrainskaya NPP – 48th day of major planned maintenance on unit No. 4 of the Zaporizhzhya NPP – the 18th day of average planned repairs.

© 2017 – 2019, paradox. All rights reserved.

Check Also

LA Mayor Garcetti crowned Covid-19 ‘dictator’ after shutting off utilities at TikTok star’s Hollywood party mansion

In a tweet, Garcetti announced that he had instructed the city to disconnect utility services …

Leave a Reply

Your email address will not be published. Required fields are marked *