“Ukrenergo” will facilitate the development of a network of environmentally friendly power plants

"Укрэнерго" облегчит развитие сети экологически чистых электростанцийAlready, there is a special “window” to simplify the connection to the network “Ukrenergo”.

NEC “Ukrenergo” plans to simplify the arrangements for issuance of technical conditions and approvals of the relevant feasibility study for the creation of facilities for the production of electricity from renewable sources.

According to the head of the company “Ukrenergo” is already running in test mode single window for a potential investor that intends to build the new facility for alternative energy. The purpose of the “window” – the simplification and unification of all the procedures for connecting to the network “Ukrenergo”.

See also:  The increase in rent in the capital: it became known when and by how much

“Investors no longer have to spend time searching for information or refer to the various intermediaries who promise to “solve all issues”. I hope that the principle of “single window” will be extended to power companies, which are operators of distribution networks”, – said the head of Ukrenergo Vsevolod Kovalchuk.

Kovalchuk also spoke about another initiative which is called “Green calculator”.

“It’s simple and intuitive online algorithm for determining the connection costs and indicative technical specifications, which aims to provide the investor with information for making decisions on connecting to the network Ukrenergo”, – he said.

See also:  Russian social network will begin to "merge" the FSB data about their users

At the same time the head of Ministry of energy noted the need to increase the responsibility of investors for failure of contracts.

“Now we signed 9 contracts with investors of wind and solar power plants for a total capacity of over 1600 MW. But only one of the contract conditions are fully met, and the facility is prepared to connect. Other projects are slow in the design phase. This situation should be corrected. We intend to strengthen the responsibility for failure to fulfill investor obligations,” he added, Kovalchuk.

© 2017, z-news.link. All rights reserved.

Check Also

Ukrainians told how much it would cost to rent for New year

The earlier you book an accommodation, the cheaper it will cost. The most popular places …

Leave a Reply

Your email address will not be published. Required fields are marked *